Redacted
Structural
- Mar 12, 2016
- 160
Hi there,
I am working on a strut design and I am finalizing the connection details.
The steel strut is 5.2m long and has a temperature range of 32 degrees C. This results in a thermal expansion of 2mm. When converting this into a force it would result in 1337kN (which I do not want to impart into the buttresses that the strut is connected to). The existing buttresses are stiff as they increase in depth as you go down (triangular), so I can't see these deflecting to relieve the expansion.
For an anchor base plate connection as shown below, would there be enough give in the bolted connection to account for a 2mm expansion? If so, is there any literature to back this up that you can share or name?
I am trying to determine if I need to include some form of elastomeric bearing material under the base plate to accommodate this 2mm expansion movement. Is there a better/simpler way to approach this?
I am also thinking of ways to increase the construction tolerances on site. I have allowed for 2" of non-shrink high strength grout on both sides but I am wondering if any additional measures should be added such as oversized/slotted holes to the base plate etc? The contractor would essentially place the steel beam with a crane from above. I'm thinking that the anchor holes will need to be pre-drilled prior to placing the beam and the anchors put in after the beam is levelled and in position.
Any advice would be greatly appreciated.
I am working on a strut design and I am finalizing the connection details.
The steel strut is 5.2m long and has a temperature range of 32 degrees C. This results in a thermal expansion of 2mm. When converting this into a force it would result in 1337kN (which I do not want to impart into the buttresses that the strut is connected to). The existing buttresses are stiff as they increase in depth as you go down (triangular), so I can't see these deflecting to relieve the expansion.
For an anchor base plate connection as shown below, would there be enough give in the bolted connection to account for a 2mm expansion? If so, is there any literature to back this up that you can share or name?

I am trying to determine if I need to include some form of elastomeric bearing material under the base plate to accommodate this 2mm expansion movement. Is there a better/simpler way to approach this?
I am also thinking of ways to increase the construction tolerances on site. I have allowed for 2" of non-shrink high strength grout on both sides but I am wondering if any additional measures should be added such as oversized/slotted holes to the base plate etc? The contractor would essentially place the steel beam with a crane from above. I'm thinking that the anchor holes will need to be pre-drilled prior to placing the beam and the anchors put in after the beam is levelled and in position.
Any advice would be greatly appreciated.