I have an instance where I need to reinforce an existing beam. The building was constructed back in 1984 and consists of cantilever beam construction. I am trying to increase the load on the beam and I am getting killed by the unbraced length of the bottom flange (I am using the distance between the supports). My solution, at the moment, is to weld a plate on the bottom flange of the beam. I would like to avoid having to weld something to the top flange as there are stiffeners at the supports making continuity of the reinforcing difficult.
The problem I am having is with equation F4-9a and F4-9b of the AISC 13th edition manual in particular how these equations relate to table B4.1 case 11. In my instance for negative bending over the support I end up with the PNA in the flange of the beam therefore I do not know what to use for lam-pw. If I don't know lam-pw then I don't know if I should use equation F4-9a or F4-9b...... I am guessing that I would use F4-9a but I am not sure.
The problem I am having is with equation F4-9a and F4-9b of the AISC 13th edition manual in particular how these equations relate to table B4.1 case 11. In my instance for negative bending over the support I end up with the PNA in the flange of the beam therefore I do not know what to use for lam-pw. If I don't know lam-pw then I don't know if I should use equation F4-9a or F4-9b...... I am guessing that I would use F4-9a but I am not sure.