Hi,
I hope someone can help me out of this. I have an industry site here. Originally? it was spec. as 100mm crushed gravel and 200mm pit-run with 98% SPD compaction. Then the contractor told me if I can reduce 98% SPD to 95% SPD, the compaction cost can drop 40%. So, any thought of that or any resource that I can take a look?
Thanks a lot!
JYF
I hope someone can help me out of this. I have an industry site here. Originally? it was spec. as 100mm crushed gravel and 200mm pit-run with 98% SPD compaction. Then the contractor told me if I can reduce 98% SPD to 95% SPD, the compaction cost can drop 40%. So, any thought of that or any resource that I can take a look?