In one of my company previous project, someone who is no longer in this company designed a flat slab. The floor is added half-way in between existing floors. They drilled the rebars into the existing columns. Enlarge the column below the new floor by 200 mm on each side and become 1400x1400 (originally 1000x1000). What should be the stiffness column or is it pin support? He used only 5% stiffness.
Thanks
In one of my company previous project, someone who is no longer in this company designed a flat slab. The floor is added half-way in between existing floors. They drilled the rebars into the existing columns. Enlarge the column below the new floor by 200 mm on each side and become 1400x1400 (originally 1000x1000). What should be the stiffness column or is it pin support? He used only 5% stiffness.
Thanks