Now, I'm planing to prepare the air blowing of test procedure as below.
Construction Stage : ambient Lay up (A-ITR)
Pre-commissioning Stage : Dry Lay up (B-ITR, Immediately after dewatering, start drying the system to a dew point that will ensure a dew point of -1°C or less at the final lay-up pressure at all exit points)
"ambient lay up shall be carried out as below
A. Test water shall be drained completely.
B. Air blowing shall be carried out to remove water until no visible trace of water is present."
However, Client request me to propose acceptance criteria of ambient lay up.
as i understand, ambient lay up will be inspected as canvas.
Could you advise to me for above mentioned concern.
Construction Stage : ambient Lay up (A-ITR)
Pre-commissioning Stage : Dry Lay up (B-ITR, Immediately after dewatering, start drying the system to a dew point that will ensure a dew point of -1°C or less at the final lay-up pressure at all exit points)
"ambient lay up shall be carried out as below
A. Test water shall be drained completely.
B. Air blowing shall be carried out to remove water until no visible trace of water is present."
However, Client request me to propose acceptance criteria of ambient lay up.
as i understand, ambient lay up will be inspected as canvas.
Could you advise to me for above mentioned concern.