Melzar
Civil/Environmental
- Apr 1, 2008
- 10
We have a disagreement about how to estimate the pile length for driven piles using AASHTO LRFD.
The AASHTO LRFD says that static analysis should be used to estimate the pile length, even if a load test or other method will be used during production. So to estimate the length:
phi (static) x Rn (static) = phi (dynamic) x Rn (dynamic)
As an example, consider a 60 kip factored resistance pile. Let's say that we use static analysis with phi=0.4 to estimate the length. So we have to design for a nominal resistance of 60 kips/0.4 = 150 kips. Let's say that this gives us an estimated length of 40 ft. To get the same factored resistance using the dynamic testing, let's say phi=0.65, we need a lower nominal resistance - 60 kips/0.65 = 92.3 kips.
Does this mean that we can expect a dynamic nominal resistance of 92.3 kips for the 40 ft length?
It seems to me that the equation tells us that we have equal confidence in the piles on either side of the equation - not that they are the same pile! The static analysis will give us the average nominal capacity for the pile - the actual capacity is just as likely to be higher as it is lower. So shouldn't we target the dynamic nominal resistance with our static analysis when we are trying to estimate pile length?
In the example, we desire a 60 kip pile and we are using dynamic testing (phi = 0.65). So the required nominal resistance is 92.3 kips. Shouldn't we use static analysis to target 92.3 kips, then, for our estimated length. The estimated pile length would be just as likely to be short as long.
If we use the lower static resistance factor to estimate the length, wouldn't a "smart" contractor identify that the production piles would be shorter, resulting in a jacked bid process?
Am I off base? How do you all determine an estimated length - the AASHTO LRFD static method, or engineering judgment? If the static methods are used with the lower resistance factors, do the production piles consistently end up shorter?
Thank you,
Melzar
The AASHTO LRFD says that static analysis should be used to estimate the pile length, even if a load test or other method will be used during production. So to estimate the length:
phi (static) x Rn (static) = phi (dynamic) x Rn (dynamic)
As an example, consider a 60 kip factored resistance pile. Let's say that we use static analysis with phi=0.4 to estimate the length. So we have to design for a nominal resistance of 60 kips/0.4 = 150 kips. Let's say that this gives us an estimated length of 40 ft. To get the same factored resistance using the dynamic testing, let's say phi=0.65, we need a lower nominal resistance - 60 kips/0.65 = 92.3 kips.
Does this mean that we can expect a dynamic nominal resistance of 92.3 kips for the 40 ft length?
It seems to me that the equation tells us that we have equal confidence in the piles on either side of the equation - not that they are the same pile! The static analysis will give us the average nominal capacity for the pile - the actual capacity is just as likely to be higher as it is lower. So shouldn't we target the dynamic nominal resistance with our static analysis when we are trying to estimate pile length?
In the example, we desire a 60 kip pile and we are using dynamic testing (phi = 0.65). So the required nominal resistance is 92.3 kips. Shouldn't we use static analysis to target 92.3 kips, then, for our estimated length. The estimated pile length would be just as likely to be short as long.
If we use the lower static resistance factor to estimate the length, wouldn't a "smart" contractor identify that the production piles would be shorter, resulting in a jacked bid process?
Am I off base? How do you all determine an estimated length - the AASHTO LRFD static method, or engineering judgment? If the static methods are used with the lower resistance factors, do the production piles consistently end up shorter?
Thank you,
Melzar