Blackberry77
Electrical
- Apr 5, 2010
- 9
We have a Client that is requesting a 7 MVA motor upgrade at their facility by adding a 44kV-600V power transformer and some switchgear. Now, this as a requirement requires switchgear with ~7000 A requirement at 600 V. This would not be an easily obtained item. Would our best bet to split the number of transformers into more with multiple switchgear lineups or are there more economical options?