Denob
Civil/Environmental
- Feb 11, 2005
- 28
Project Description: 29,000 L.F. of 30” OR 24” water transmission main and 8,000 L.F. of 16” water main—all within road right-of-way. The waterline will be 4 to 8 feet behind the edge of asphalt of a 2-lane (one lane each direction) heavily trafficked open-ditch roadway. The depth will generally be 6 to 8 feet deep, except when crossing flood control channels, canals, gas/petroleum pipelines, and a railroad. Possible pipeline materials are PVC, Ductile Iron, and Steel (concrete pipe disqualified due to recent failures in this area). I have several design questions that are probably common for large diameter pipeline projects:
1. I assume PVC (C-905) is the cheapest pipe material for 16” but what about 24” and/or 30”? The latest I was able to come up with was $81 per foot for 30” ductile iron and $83 per foot for 30” PVC (material and shipping only).
2. What would be acceptable wall thicknesses or DR’s? The typical operating pressure will be about 70 psi. I would like to get the cheapest pipe I can without compromising longevity and reliability.
3. Assuming costs are the same for each material, which material is the best? I am leaning toward PVC because of its non-corrosive nature.
4. Concerning vertical changes in elevation, at what depth should I consider having bends instead of deflections? Does it make much difference hydraulically (maybe it’s better to use 22.5 deg. bends)? For example, if I needed to drop the current elevation by 5 feet in order to obtain minimum clearance with a flood control channel, would it be better to have 4x45 deg. bends, 4x22.5 deg. bends, or to have the water line deflect down to meet clearance requirements (let’s assume ½ foot offset per 20 segment—or 200 feet of horizontal distance required to drop 5 feet vertically)? It is my understanding that fittings such as bends are expensive for pipe at this diameter. At the same time, using bends would require less excavation.
5. How often and at what locations should Combination Air Release Valves be located (no surge analysis to be done)? I understand that ARV’s are most effective at peaks, but is this always necessary? What if there’s only a slight deflection in the waterline? It seems excessive to place an expensive ARV at even the most minor peaks. In my preliminary design, I am pairing the ARV’s with a Butterfly Valve at every 3000 ft. Is this adequate spacing for ARV’s? Any general advice on ARV’s if no surge analysis will be done?
These are the only questions I can think of right now. Any help on any of the above questions is greatly appreciated.
1. I assume PVC (C-905) is the cheapest pipe material for 16” but what about 24” and/or 30”? The latest I was able to come up with was $81 per foot for 30” ductile iron and $83 per foot for 30” PVC (material and shipping only).
2. What would be acceptable wall thicknesses or DR’s? The typical operating pressure will be about 70 psi. I would like to get the cheapest pipe I can without compromising longevity and reliability.
3. Assuming costs are the same for each material, which material is the best? I am leaning toward PVC because of its non-corrosive nature.
4. Concerning vertical changes in elevation, at what depth should I consider having bends instead of deflections? Does it make much difference hydraulically (maybe it’s better to use 22.5 deg. bends)? For example, if I needed to drop the current elevation by 5 feet in order to obtain minimum clearance with a flood control channel, would it be better to have 4x45 deg. bends, 4x22.5 deg. bends, or to have the water line deflect down to meet clearance requirements (let’s assume ½ foot offset per 20 segment—or 200 feet of horizontal distance required to drop 5 feet vertically)? It is my understanding that fittings such as bends are expensive for pipe at this diameter. At the same time, using bends would require less excavation.
5. How often and at what locations should Combination Air Release Valves be located (no surge analysis to be done)? I understand that ARV’s are most effective at peaks, but is this always necessary? What if there’s only a slight deflection in the waterline? It seems excessive to place an expensive ARV at even the most minor peaks. In my preliminary design, I am pairing the ARV’s with a Butterfly Valve at every 3000 ft. Is this adequate spacing for ARV’s? Any general advice on ARV’s if no surge analysis will be done?
These are the only questions I can think of right now. Any help on any of the above questions is greatly appreciated.