during floor repairs a section of 1st ring shell is to be cut out to permit access for plate installation ,typically called a doorsheet , contractor wants to cut the shell plate 3" above the shell to bottom weld and re install this plate after floor is finished. looking @ API 653 under section 9 it seems the minimum dimension for horizontal welds to the bottom weld is 6" anyone agree
 
Concur that is what the book says. The Tank Engineer or the API 653 Inspector for that tank could waive that requirement in writing [file this in the tank's file]. Practically, 6" is not that much farther up on the shell, and allows for a larger 'heel' of remaining slop & crud left in the tank. I'd need a fairly compelling Reason [vs. contractor's 'we always do it this way'] to waive this minimum spacing requirement.
 