Verner
Mining
- Jul 7, 2003
- 24
We would like to produce a "100-Day Schedule" from our current schedule (duration of this schedule is 5 years)Displaying only resource activities both on the Gantt Chart and in resource activities. When we filter for "date range" it will display that occur in this time frame and display them from their start to completion dates no matter what date they end and we don't want this. Is there an easier way?
Thanks
Thanks