We would like to produce a "100-Day Schedule" from our current schedule (duration of this schedule is 5 years)Displaying only resource activities both on the Gantt Chart and in resource activities. When we filter for "date range" it will display that occur in this time frame and display them from their start to completion dates no matter what date they end and we don't want this. Is there an easier way?

Thanks
 
Replies continue below

Recommended for you

The "Date range..." filter asks for any task that has a finish date greater than or equal to your first input and a start date less than or equal to your second input.

What you are looking for is the other way around!

You want any task that has a finish date less than or equal
to your first input and a start date that is greater than or equal to your second date.

Make a copy of "Date range.." and change the 'test' in each line.