Hi,
I am working on a very large development project (2000 homes at buildout), for which the city is requiring the developer to install wells to provide water supply. The developer does not want an elevated tank on the site and there is a connection to the county system for emergency water demands. I am asking for input on controlling the well pumps by system pressure or another option other than tank level. They are performing test wells now so I dont know the production capacity of each well yet but I expect each well to produce around 150-200 gpm and there will be several.
I dont have experience with hydropnuematic tanks so I was looking for some guidance here for sizing.
Thanks for your help.
Off the cuff, depends upon the State and County possibly municipality or City, but as a rule of thumb, The Drinking Water Permit Requirements for California, see Title 22 Drinking Water Permit. Plan for Maximum Daily Demand, and the System Capacity as a whole must support the Maximum Daily Demand over a long period say 10 yrs. For Fire Flows, must meet 4x Peak Hourly Flow, say 2x 1800gpm Fire Hydrants ( 2 x 1800 gpm x 60min/hr x 4 hr = X gal/4hr PHF) Plus peak hourly flow normal conditions within the Distribution System (usually morning or dinnertime),
For a small system supporting about 20,000 people, it's Max Daily Demand was 6.4MGD, while Avg Daily Demand ranged from 1MGD to 3.5MGD, annual peak about 4-5MGD in late summer.
I suspect you are looking at a 1-4 MG Above ground Ground water storage tank, either a pressure tank or change in elevation for gravity feed, to keep say 30 psi in the system. (No more than 84-100 psi, throughout the Distribution System.) Probably fed by 2-12 wells with 1-3 running fairly routinely, say specific gravity well pumps producing about 1000 gpm each (no less than about 600gpm ea). Depends on groundwater chemistry, and production rates, how deep they are, how many aquifers they must pass through for drinking water quality production.
Some states require the developer to dedicate the funding up front for the utility buildout. Some do not, say Colorado, notorious for bonds placed on parcel owners costing more than any home built on the property to complete min utility costs.
Regarding well pump controls. Might look at a Wet SCADA system to assist your efforts.
Pump Controllers will likely used VFDs, but calling for pump startup will always be tied to the water level in the reservoir which needs to be filled. Typically each Closed Reservoir (Water Tank) will have a LLow, Low, High, HHigh level, which triggers how many wells need to operated to refill the Reservoir. If it is a gravity fed system, the pressure will be related to the water level in the tank. Some 1MG tanks in MUDS around Texas use Pressure Tanks sized to about 20,000-50,000gal (not uncommon in the 80s). Either the reservoir is pumped with water at an elevation from which it gravity feeds the Distribution System, or you use Pressure Tanks to pressurize the Distribution System. If the terrain doesn't support adequate change in elevation, then either pressure tanks or an elevated Water tank (Water Tower) would be required. Same amount of power required to lift the water to the higher elevation or maintain a pressure tank. Might be able to have pumps on line, but would require a high level of redundancy and continuous ops or high fluctuation in operations. I haven't designed or seen such a system, but controls and pump wise, the technology is there.
No matter what you do, the Authority Having Jurisdiction will likely require a Civil PE or EnvrEngr PE to submit an Engineering Report, from which the State would issue the Drinking Water Permit. That Engr Rpt would have to comply with all federal, state, county, and municipal laws, stds, and codes for approval to operate to serve as a public water supply.
For 2000 homes, a population of just under 5000, you'd still have to have evacuation routes, egress, ad ingress, Circulatory Routes, Potable Water and Fire Mains, .... 2024 costs, 0.5MG tank at about $3.5mil; Specific Gravity pumps and casing for existing well, about $350k ea. Old 2000 rule of thumb for DistSys piping was Line Size (Dia inches) x $10/LF for 36in deep to TOP OG buried PWTR lines.
Emergency connections to other systems, can also flow both ways. Verify with the County. Good luck, how this helps.