Welding pipes 40 ft underground
Welding pipes 40 ft underground
(OP)
Hello,
Does anyone here have any experience with welding down in a 40 ft temporary pit? For a project, two pipes need to be welded together but this weld needs to take place 40 ft below grade. We are planning to construct some sort of temporary steel caisson with pumps running continuously to keep the water out.
I am in the process of researching what our options are, not working on a design or spec yet.
Does anyone have some experience with this or can point me in the right direction to see how this is commonly done?
Thank you
Does anyone here have any experience with welding down in a 40 ft temporary pit? For a project, two pipes need to be welded together but this weld needs to take place 40 ft below grade. We are planning to construct some sort of temporary steel caisson with pumps running continuously to keep the water out.
I am in the process of researching what our options are, not working on a design or spec yet.
Does anyone have some experience with this or can point me in the right direction to see how this is commonly done?
Thank you
RE: Welding pipes 40 ft underground
Might need some ventilation, but depends on your design of the caison.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Welding pipes 40 ft underground
RE: Welding pipes 40 ft underground
People weld things in all sorts of environments given the right conditions. this sounds a bit like you're trying to do it on the chaep?
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Welding pipes 40 ft underground
Proper excavation, reinforcement, access and evacuation ability, along with ventilation are critical to worker safety.
It the workers are not comfortable and safe you won't get usable welds.
= = = = = = = = = = = = = = = = = = = =
P.E. Metallurgy, consulting work welcomed