Tube to Tube Sheet Mock up (Performance Qualification) QW-193.2
Tube to Tube Sheet Mock up (Performance Qualification) QW-193.2
(OP)
Back Ground:
A welder welded 10 tubes in which one tube rejected in visual test and two in macro examination but other 7 tubes accepted in visual, PT and macro examination.
Question:
Is welder qualified as per QW-193.2 " a minimum 05 tubes are required for qualification".
Reference attached.
Regards,
Fahad
A welder welded 10 tubes in which one tube rejected in visual test and two in macro examination but other 7 tubes accepted in visual, PT and macro examination.
Question:
Is welder qualified as per QW-193.2 " a minimum 05 tubes are required for qualification".
Reference attached.
Regards,
Fahad
RE: Tube to Tube Sheet Mock up (Performance Qualification) QW-193.2
You have 5 x acceptable so theoretically the welder has passed.
However, the code provides minimum requirements - it is up to you as the representative of the employer to decide on acceptability of the welder.
3 x DNC from 10 x welds - a 30% failure rate. Not acceptable.
This is only my opinion but if I was in your position I would have the welder weld a further 5 x tubes and all 5 must pass.
RE: Tube to Tube Sheet Mock up (Performance Qualification) QW-193.2
RE: Tube to Tube Sheet Mock up (Performance Qualification) QW-193.2
Regards
RE: Tube to Tube Sheet Mock up (Performance Qualification) QW-193.2
Thanks for your comments,