IRC Grading Requirement
IRC Grading Requirement
(OP)
I am building a new covered patio (roof supported by 6x6 posts) and am concerned about the slope of the concrete slab, or rather the lack of it. I put a 4 foot level on many places on the slab and it's essentially dead on level. I am under the 2015 IRC and section R401.3 states "Impervious surfaces within 10 feet of the building foundation shall be sloped a minimum of 2 percent away from the building". The building inspector does not inspect slabs in my municipality so I'm getting no help there.
When the concrete contractor came out he claimed to not know what the code says and also say it doesn't matter because the patio is covered. I've always done it like this, blah, blah, blah. I talked to another home builder and he said he always uses 1/4" per foot (i.e. 2%) for porches, patios, driveways and even garage floors. I live in Oklahoma and we regularly receive torrential downpours with 70 mph winds, so water will blow up on the patio as it faces south. I checked my front porch and it's 1/4" per foot or very close. Obviously the contractor is not going to admit he did anything wrong.
Regardless, the code does not differentiate between impervious surfaces covered by roofs, but no walls. Anyone ever ran into this before? Thanks
When the concrete contractor came out he claimed to not know what the code says and also say it doesn't matter because the patio is covered. I've always done it like this, blah, blah, blah. I talked to another home builder and he said he always uses 1/4" per foot (i.e. 2%) for porches, patios, driveways and even garage floors. I live in Oklahoma and we regularly receive torrential downpours with 70 mph winds, so water will blow up on the patio as it faces south. I checked my front porch and it's 1/4" per foot or very close. Obviously the contractor is not going to admit he did anything wrong.
Regardless, the code does not differentiate between impervious surfaces covered by roofs, but no walls. Anyone ever ran into this before? Thanks
RE: IRC Grading Requirement
A 2% slope would be what I would want too but I dont think you can make the contractor re-do for the simple fact that you didnt say put a 2% slope on it.
(Edit- I would have a different opinion if it was the driveway to your house. But a covered patio, I think you would have needed to specify. Thats based on my interactions with builders in my own area. It is very monkey see monkey do, no initiative.)
RE: IRC Grading Requirement
I agree with you that a lot of builders are lazy and set in their ways. They have a "I've always done it this way, so that's the right way" attitude.
RE: IRC Grading Requirement
The slab should have been sloped regardless of roof. It is not uncommon to have wind with rain/snow. There will be water on the slab that will not drain.
RE: IRC Grading Requirement
If the building inspector does not inspect slabs, then you become the "inspector". Did you tell the contractor how to slope the slab? Did you watch the contractor or ask about it during construction?
RE: IRC Grading Requirement
So strange to see the singularity approaching while the entire planet is rapidly turning into a hellscape. -John Coates
-Dik
RE: IRC Grading Requirement
A good reputable contractor that does regular concreting for drives etc should not the min slope. At the same time, contractors are often "I only did what you told me to do, and you didnt tell me to put a slope on it".
At the same time if its only open on one front and has a roof, I wouldnt be overly worried. It needs to be wind blown rain, blowing towards your open thats going to throw some rain it there.
Is it enough to make the contractor re do the concrete, IMO, no.
RE: IRC Grading Requirement
Is there a warranty period for the work? If so, make sure you inform of this in writing and observe it during the warranty period. If it doesn't perform, force them to fix it. If it's not a problem, then it's not a problem. No warranty? Get them to give you one or have them re-do it if you're sufficiently concerned. But the question there is, is it worth going to court over it to fight a lien claim when you withhold payment?
RE: IRC Grading Requirement
Did you pull a permit for this (or did the contractor) because if so, you have a path to force them to fix it.
The contractor 'not knowing what the code says' means nothing; ignorance of the code does not grant permission to violate it. If it did, every contractor in the world would claim to not know how to read and we'd just build whatever we wanted. Not so.
RE: IRC Grading Requirement
RE: IRC Grading Requirement
RE: IRC Grading Requirement
RE: IRC Grading Requirement
RE: IRC Grading Requirement