×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Radiant Slab Install

Radiant Slab Install

Radiant Slab Install

(OP)
I am building a 33 ft x 31 ft. garage with a radiant slab. The sandwich will be 4” washed stone, vapor barrier, 2” foam, radiant tubing stapled to the foam, 6x6 WWF on top and maybe a rebar grid on some chairs and 4-5” of concrete. Based on the layout of the doors, it would be nice to break the slab up into 6 chunks of 11 ft x 15.5 ft.
My question involves control joints. I am going to epoxy coat the slab if it makes any difference in your answers. I will also discontinue the WWF and rebar at the joints. I am concerned about using a soft-cut saw as it may hit a line if they are not careful. I have used keyway on previous slabs and it worked ok but the concrete starting chipping adjacent to it. I have also done two checkerboard pours that worked amazingly well but I don’t know that I want the expense of that on this project as I need to rent a pump twice and the labor basically doubles. My other thought is to use tooled joints but don’t have too much experience with them other than I always see cracks running adjacent to them in tract homes. Maybe if they did a 2” deep joint, that would be more effective. Is that even possible? I welcome your thoughts and ideas. My other question involves the safety of the piping during the concrete placement. Will the WWF somehow puncture the tubing with all the workers scurrying around on top of it? I have heard a few isolated cases of that.

Thanks

RE: Radiant Slab Install

XR - if you're going to use rebar, why do you have WWR in there, too?

I typically spec saw cut crack control joints. When the concrete is just firm enough to take the saw without tearing out aggregate - about 6 to 12 hours, but closer to 6 - they run the saw with the blade set to 1" for a 4" slab on grade. It takes careful coordination to make sure the cut lines up with the interrupted reinforcement (wire or bars). But this would protect your tubing as long as they keep the depth of the kerf locked in.

I don't have any experience with tooled joints - most of the contractors around here seem to prefer saw cutting - but the tract homes I've seen with the problem you mention is usually due to cuts happening a day or more after the slab has been poured. The damage is done by then, and it just takes a bit more time for the cracks that had already formed to open up and become visible. That's if they joint the slab at all. A lot of the cheap developers just don't bother - let it crack and cover it with carpet/laminate flooring.

RE: Radiant Slab Install

(OP)
The WWF is there to keep the tubing down. The staples like to pull out of the foam and the tubing wants to float.
Good point on the cutting. I could be pretty generous with the tubing and rebar space near the cut.

Thanks!

RE: Radiant Slab Install

(OP)
Another issue is the concrete guy does not like admixtures and this will be placed in January so it may not cure fast enough for him to cut unless he brings a sleeping bag.

RE: Radiant Slab Install

If you’re worried then you could always use a zip strip instead of saw cutting it.

RE: Radiant Slab Install

(OP)
Ahh, never seen those before - pretty cool.

RE: Radiant Slab Install

Just a word of warning - ACI 360 recommends NOT using plastic inserts to form crack control joints in slabs with wheel traffic. My guess is that while it forms a nice weak plane, it probably disengages the aggregate on either side of the crack too much to provide any sort of post-crack shear friction/aggregate interlock to keep the surfaces flush as large point loads roll over the joint. For a garage, you might be able to avoid it by keeping the zip strips parallel to the direction of traffic or including smooth dowels placed just below the bottom of the strips if you're going to have a pull through.

As for timing early entry saw cuts...maybe a late night pour and an early morning saw cut? Or an early morning pour with heaters and blankets. The latter is probably better.

RE: Radiant Slab Install

If using WWF for the bottom, and place your reinforcing 1-1/2" from the top, why not sawcut... and at the right time. Zip strips work, too.

Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?

-Dik

RE: Radiant Slab Install

(OP)
After discussing this with my concrete sub and honoring his skill set and tools, I think I’m gonna end up doing keyway. Thanks for all the advice!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close