INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

End plate moment connection

End plate moment connection

End plate moment connection

(OP)
Hey Guys,
I just wonder about this one, why generally we have to separate top and bottom bolt groups for endplate connection? what if the bolt has been provided continuously throughout the web of the beam?

I knew that the top group bolts were in tension and bottom one in compression, then what was my concern is

Should not we provide bolt at the center of the web where rounded in red? so that, why?

when I have moment force and shear force, I should count on flange bolts (bolts that near to flange both above and below) for moment and web bolts for shear.


Thanks in advance!!

RE: End plate moment connection

Vee0007, get a trail version of https://www.ideastatica.com/

You should be able to see the results in detail.

However the centre bolt is often provided on deep connections to not have the plate come away from the member and show a gap.

http://www.nceng.com.au/
"Programming today is a race between software engineers striving to build bigger and better idiot-proof programs, and the Universe trying to produce bigger and better idiots. So far, the Universe is winning."

RE: End plate moment connection

You can understand the reason by looking at the beam stress diagram due to moment - where are the maximum/high stresses located, and how the stresses vary from the flanges toward the geometry center. Also, we often design the connection using the simplification, T = C = M/d, that assumes the flanges carry the majority of the applied force, thus, that are the locations the blots bolts to be placed.

RE: End plate moment connection

Quote:

stresses vary from the flanges toward the geometry center

Great guess... that and the beam acts as a stiffener and the connection of the end plate is pretty stiff...

Dik

RE: End plate moment connection

Quote:

why generally we have to separate top and bottom bolt groups for endplate connection?

There are two reasons why we do it this way that I can think of.
1) To avoid shear / tension interaction in the bolts. For Bolted End Plate connections, the assumption is that the bolts on the tension side of the connection resist ONLY tension and do NOT contributed to the shear resistance of the connection. Likewise, the bolts on the compression side are viewed to resist ONLY shear and do not resist any tension. Not technically, true. But, it's conservative and it's convenient.

2) The yield line method is concerned with the transfer of the tension flange force into the plate and the bolts. Right? The further away from the tension flange you get, the less effect those bolts will have on the plate yield lines.

RE: End plate moment connection

If you design assuming elastic behavior, the centroid of the connection is at the center.
So, bolts placed in the center there will have 0 strain , and won't contribute to the moment capacity.

RE: End plate moment connection

Quote:

The further away from the tension flange you get, the less effect those bolts will have on the plate yield lines.

So you can use a thinner plate in the middle?bigsmile

Dik

RE: End plate moment connection

dik,

You can carve the middle out...

RE: End plate moment connection

Quote:

You can carve the middle out...
I was just jokin', but years back I was wondering what the effects of adding the end plate to only the top and bottom... not likely cost effective.

Dik

RE: End plate moment connection

I was kidding too. I think its attractiveness is ease of fabrication, and ease in design. Erection may not be that easy though.

RE: End plate moment connection

Quote (Veer007)

knew that the top group bolts were in tension and bottom one in compression,
There are no bolts in compression. Also the moment direction determines whether top or bottom bolts are in tension.

Quote (Veer007)

web bolts for shear.
you can't force the shear load in a moment connection to go to the web bolts only; shear is hard-headed

RE: End plate moment connection

End plates at the bolts only won't align good. Full length plates can align bolt holes unless you really mess up attaching them. Partial plates top and bottom may leave one set not aligned at all.

RE: End plate moment connection

(OP)

Quote (rowingengineer)

Vee0007, get a trail version of https://www.ideastatica.com/
can't we use this offline? this one asks more detail IP address, port etc

Thanks in advance!!

RE: End plate moment connection

(OP)
So, top bolts resist tension/moment creating tension, and bottom bolts should be counted for shear, okay?

But perhaps when there a reversible load condition, the bottom bolts should be in tension, right. Am I wrong?

Thanks in advance!!

RE: End plate moment connection

Sorry veer007 while I love the software I really have no idea about the way it runs offline or similar.

http://www.nceng.com.au/
"Programming today is a race between software engineers striving to build bigger and better idiot-proof programs, and the Universe trying to produce bigger and better idiots. So far, the Universe is winning."

RE: End plate moment connection

Quote:

and bottom bolts should be counted for shear, okay?

Both top and bottom bolts are counted for shear. While the top bolts have to be checked for the combined tension and shear, the bottom bolts checked against shear only, unless there is force reversal.

RE: End plate moment connection

(OP)

Quote (rowingenginner)

Thanks no problem

Thanks in advance!!

RE: End plate moment connection

(OP)

Quote (retired13)

Your last post make me clear.

But still I am not clear about the gap between bolt groups.

I thought I should not provide bolt at centre or I could count this for shear if I provided bolts at centre?

Thanks in advance!!

RE: End plate moment connection

Yes, for excessive shear demand, bolts can be provide in the middle for that purpose. But, since the bolts in the middle do not contribute, or contribute very little, in resisting the bending, the additional bolts will only escalate the cost, if the bolts on the flanges are adequate to handle both (bending and shear). Note that the end plate connection is usually provided for beams with considerable amount of moment that calls for deep section, but the tension and compression are concentrated on the flanges only, so it leaves huge space in between.

RE: End plate moment connection

(OP)
Also, why do we need a thicker plate? do endplate yield stress need more than connection beam?

Thanks in advance!!

RE: End plate moment connection

Veer007,

Plate thickness is by design to satisfy bolt bearing, and flange tension. Note that the tension is considered to be resisted by a tee in a hanger situation, for which prying force needs to be evaluated, that increases strength demand.

RE: End plate moment connection

Thicker end plates have a big influence on the effects of prying action which influences the residual strength for shear.

Dik

RE: End plate moment connection

Plate thickness is also based on bending of the plate as the effect of the bolt tension migrates from the bolt to the stiffener or flange.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

White Paper - Reshoring Prototyping and Production
In this whitepaper, we'll provide insight into why and when it makes sense for U.S. manufacturers to reshore prototyping and production, and how companies can leverage the benefits of working with local design, prototype, and manufacturing partners during the pandemic and beyond. Download Now
Engineering Report - Top 10 Defect Types in Production
This 22-page report from Instrumental identifies the most common production defect types discovered in 2020, showcases trends from 2019 to 2020, and provides insights on how to prevent potential downtime in 2021. Unlike other methods, Instrumental drives correlations between a variety of data sources to help engineers find and fix root causes. Download Now
White Paper - Addressing Tooling and Casting Requirements at the Design Stage
Several of the tooling and casting requirements of a part can be addressed at the design stage. If these requirements are not addressed at the design stage, lot of time is spent in design iteration when the design reaches the die caster. These design issues lead to increase in time and cost of production leading to delay in time to market and reduced profits for the organization. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close