Welding Non-NACE Attachments to NACE Piping
Welding Non-NACE Attachments to NACE Piping
(OP)
Dear all,
Is there any standard or recommended practice that clearly states it's acceptable to weld non-NACE attachments (e.g., normal ASTM A1006-B pipe saddles, earthing/bonding lugs made of ASTM A36, etc.) to the external of a A106-B MR0103-compliant pipe? The piping is in sour service; hence the MR0103 requirement. The project specification does say that saddle material shall be the same as pipe material, but mistake has been made and hundreds of non-NACE A106-B saddles have been welded to NACE pipes.
I looked through MR0103 Nov 2015, and couldn't find any answer.
Thanks in advance.
Is there any standard or recommended practice that clearly states it's acceptable to weld non-NACE attachments (e.g., normal ASTM A1006-B pipe saddles, earthing/bonding lugs made of ASTM A36, etc.) to the external of a A106-B MR0103-compliant pipe? The piping is in sour service; hence the MR0103 requirement. The project specification does say that saddle material shall be the same as pipe material, but mistake has been made and hundreds of non-NACE A106-B saddles have been welded to NACE pipes.
I looked through MR0103 Nov 2015, and couldn't find any answer.
Thanks in advance.
RE: Welding Non-NACE Attachments to NACE Piping
See the link bellow
luis
hope it helps
https://www.twi-global.com/technical-knowledge/job...
RE: Welding Non-NACE Attachments to NACE Piping
Steve Jones
Corrosion Management Consultant
www.linkedin.com/in/drstevejones
All answers are personal opinions only and are in no way connected with any employer.
RE: Welding Non-NACE Attachments to NACE Piping
Understood. Is there any official interpretation or API/EN etc. standard saying that it's ok to do so provided hardness value is maintained below the limit stated in MR0103 (thru PWHT)? I am the project owner in a refinery hoping to salvage the project schedule by avoiding unnecessary rework.
Is it common that projects out there allow welding non-NACE saddles to NACE piping?
Thanks again for your feedback.
RE: Welding Non-NACE Attachments to NACE Piping
Actually this is a grey area. However, you need to carry out PWHT to all the attachments. If this is too big a job, raise a 'deviation'.
Regards.
DHURJATI SEN
Kolkata, India
RE: Welding Non-NACE Attachments to NACE Piping
luis
RE: Welding Non-NACE Attachments to NACE Piping
where failure by SSC would (1) compromise the integrity of the pressure-containment system, (2) prevent the basic function
of the equipment, and/or (3) prevent the equipment from being restored to an operating condition while continuing to contain
pressure.
1.2.2 It is the responsibility of the user to determine the operating conditions and to specify when this standard applies."
1.2.1
Are the saddles "exposed?"
1.2.2
This is the philosophy that will NOT get you any interpretation other than 'end user to decide.'
Steve Jones
Corrosion Management Consultant
www.linkedin.com/in/drstevejones
All answers are personal opinions only and are in no way connected with any employer.
RE: Welding Non-NACE Attachments to NACE Piping
Thanks for the feedback. It is clear to me now that this is a shot I need to make.
Daniel