×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Guidance on Piping Inspection after Water Hammer Damage

Guidance on Piping Inspection after Water Hammer Damage

Guidance on Piping Inspection after Water Hammer Damage

(OP)
Introduction:
We recently built a compression plant. Each compressor has a suction scrubber. These scrubbers have process drain lines connected to a 6" SCH40 A-106 Gr-B header which runs 2 km. to a tie-in with existing plant.
Design Code: ASME B31.3

Problem:
Due to process issues, this header suffered "water hammer" damage in different sections two months after it started working. At some sections we have some "dents" due to impact with other pipes and, at some other sections, we have "gouges" due to impact with supports.
For the worst case scenario, see a photo and a sketch:
https://files.engineering.com/getfile.aspx?folder=...
https://files.engineering.com/getfile.aspx?folder=...

Solution Approach:
We have checked each spot with: visual inspection, penetrant liquid testing, PA ultrasound testing and thickness measurement. However, neither our client nor us have defined which acceptance criteria needs to be applied.
At this point, we are trying to show that the remaining thickness in the worst case scenario (6,54 mm remaining thickness / 7, 11 mm nominal thickness) is acceptable per API RP 574 which states that the Barlow formula can be used.

Guidance Required:
I'm not looking for a definite answer. Just trying to understand:
a) what steps need to be taken in order to inspect the components, asses the damages and (hopefully not) repair the components.
b) which standards need to be followed for assesment? So far, I see two options:
1-API RP 574 for a simplified assesment.
2-API 570 with help from API 579 FFS - part 12 for a quantitative assesment.
c) which standars need to be followed for repair? So far:
API 570 section 8, which relies on ASME PCC-2 guidelines.

Thanks, Ricardo.

RE: Guidance on Piping Inspection after Water Hammer Damage


Such cases are always difficult to assess.

If this were about technical safety devices, all rules would have required all dented and damaged parts replaced with new, fully tested components. Reason: unknown risk and weaknesses not detected by tests and possibly shortening the components normal lifetime.

The question here should not be which tests and procedures to use, but who has the responsibility and cost for material and personell damage, should anything happen.

If this was an airplane you would probably be grounded until replaced.

On the other hand: I have seen factories allow repeated waterhammer and even repeated dust explosions in ventilation ducts because 'usually it is a limited damage'.

Your choice!

RE: Guidance on Piping Inspection after Water Hammer Damage

Every once in a while there is an opportunity for the bosses to actually earn their money .....

This is a situation where Management has to stand up, put on their big-boy pants and make a decision...

I recommend a search for an objective outside consultant who has experience with this problem....

This will be probably be expensive, but it is also probably fair to say that your existing staff has no experience in this area.

I also doubt that your Management will do this ...


MJCronin
Sr. Process Engineer

RE: Guidance on Piping Inspection after Water Hammer Damage

Why is this in "valve engineering forum"? Pipeline and piping would have been better.

You need also to look at hardness of the dents in particular.

Excessive hardness leads to fatigue cracks and failures.

The scrapes you can grind out and lose the stress concentration sharp edges, but the dents I would cut out or re-inforce with external sleeving (epoxy or steel)

B31.3 has some pretty healthy margins of safety for pipe wall thickness, but as ever the issue is risk acceptance and consequences of failure. These are not engineering decisions.

But whatever you do make sure you test it as a new piece of pipe with a full hydro.

If the damage is less than 10% of the line I would recommend replacing those parts, but if its spread out and would require complete replacement then I can see how the pressure builds for some sort of minimal repair scheme. The problem is the long term damage done to the pipe - maybe it will last decades, maybe it won't - especially if it under a fluctuating stress / pressure scenario.

Good luck and tell us what you decide to do!

Remember - More details = better answers
Also: If you get a response it's polite to respond to it.

RE: Guidance on Piping Inspection after Water Hammer Damage

(OP)
Thank you guys for your feedback.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Research Report - How Engineers are Using Remote Access
Remote access enables engineers to work from anywhere provided they have an internet connection. We surveyed our audience of engineers, designers and product managers to learn how they use remote access within their organizations. We wanted to know which industries have adopted remote access, which software they are using, and what features matter most. Download Now
eBook - Managing the Context of Product Complexity Using the Digital Twin
Keeping track of changes to complex products is difficult—think Aerospace & Defense equipment, new generations of commercial aircraft, and software-based automobiles. A new way to managing the digital context of the physical product is required and the answer is the Digital Twin. This ebook explores the opportunity available for Operations and Maintenance for the Digital Twin. Download Now
White Paper - Trends in Industrial Filtration
Substantial progress has been made in filtration technologies in recent years. New filter media materials, designs and processes have led to filters that are more efficient, reliable, compact and longer lasting. This white paper will discuss the various trends that are impacting operational responsibilities of MROs today and the resources that are available for staying up-to-date on the latest filtration solutions. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close