INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Related Articles

Jobs

ASME BPVC Sec. I Table PW-39

ASME BPVC Sec. I Table PW-39

ASME BPVC Sec. I Table PW-39

(OP)
In ASME Sec. I Tabe PW-39-1 and PW-39-2 postweld heat treatment requirements are specified based upon the material thickness.The last colum of the table covers material thickness over 5 inch (125mm) but the explanation for the holding time is like this : " 2 hr plus 15 min for each additional ,inch (25mm) over 2 inch (50mm)"

My qustion is : The last column covers material thickness over 125 mm but the holding time refers to "over 50 mm "

Isn't this a contradiction?

If not , what is the explanation?

Thank you...

RE: ASME BPVC Sec. I Table PW-39

There is no contradiction. You have a range of nominal thickness for PWHT from 2" (50mm) to 5" (125mm). The holding time beyond 2" (50mm) nominal thickness is for each additional inch (25mm) of thickness is 2 hrs and 15 minutes. This same note is repeated to even thicker material above 5" (125mm).

RE: ASME BPVC Sec. I Table PW-39

(OP)
Let's go through an example.our material thickness is 75 mm.Which column i should take?i know the requirements for the last two column is the same.but the last column also covers the previous one? The explanation for the last column in the Table PW-39-1 should be "2 hr plus 15 min for each adfitional inch (25mm) over 5 inch (125mm) just as in the Table PW-39-3.

Did you understand my problem?

RE: ASME BPVC Sec. I Table PW-39

For a nominal thickness of 75mm, you would use the column in Table PW-39-1 between 50 mm and 125 mm. The hold time would be 1 hr per 25mm thickness, so for 75mm, it would be 2 hours (1 hr per 25mm) + 2 and 15 min (for an additional 25mm) = 4 hrs and 15 minutes hold time.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close