INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Adequacy of Geotechnical Report - Pile Bridge Foundations

Adequacy of Geotechnical Report - Pile Bridge Foundations

Adequacy of Geotechnical Report - Pile Bridge Foundations

(OP)
Hi Everyone,

I have been requested by a contractor to provide a sub-structure design for a small design-build bridge replacement project in Atlantic Canada. The tender package included a geotechnical report which was tailored towards shallow foundations; however, the client has requested that bored concrete piles be used instead. The geotechnical report is fairly generic with borehole logs (13m deep), SPT values, and soil layer classification. The boreholes primarily indicate a sandy gravel mixture with few cobbles and boulders (ie, glacial till)without encountering bedrock. I am concerned that critical data and interpretation has been omitted such as: shaft friction, end bearing resistance, adhesion freezing forces (ad-freeze), etc. Not to mention recommendations from a qualified geotechnical engineer on minimum embedment length, number of piles, spacing, construction method (dry, casing, slurry, etc.), etc.

I am a civil/structural engineer with a good understanding of geotechnical, and I am able to deduce the much of the required information from the SPT-N values based on Meyerhof, soil descriptions, etc. But regardless, I feel that this information should come from a geotechnical report.

FYI, the Canadian Highway Bridge Design Code (6.7.3) re-iterates many of the same items which should be included in a geotechnical report.

Initially, the contractor agreed that they have had similar concerns from other consultants. However, my resistance to provide them a design based on the current report has resulted in them seeking out another consultant who will provide a design based on the current report.

I am very curious on what others would do in a similar situation?

Thanks!

RE: Adequacy of Geotechnical Report - Pile Bridge Foundations

You mention that originally the bridge should have been supported by shallow footings. The owner wants a piled structure and the reason is certainly for protection against scouring. The only important information, which should be part of the report, is the possible depth affected by scour.

RE: Adequacy of Geotechnical Report - Pile Bridge Foundations

It happens all the time- geotechnical services tailored toward a concept that later changes. The original geotechnical consultant should be re-commissioned to provide an assessment of the bored pile option now being requested.

Are you not in a position to request this re-assessment? Usually a small fee that goes a long way!

All the best,
Mike

RE: Adequacy of Geotechnical Report - Pile Bridge Foundations

Sounds like the geotech writing the report was not given any specific as to what the site may need, such as resistance to scour, possibly a utility trench being dug near the bridge, etc. Since that person is most familiar with the site and the borings, he (she) should be asked for more alternative recommendations, including piles. I see no reason for getting another geotech involved. While you are at it indicate he contractor would like such and such piles, etc. and what would be the comments for them? If the geotech recommended footings due to least cost, mention that higher cost for more security is OK. Chances are a professional should be able to do this at no charge. Gotta keep the clients happy should be the attitude.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close