Fillet Burn Through ASME BPVC Section I
Fillet Burn Through ASME BPVC Section I
(OP)
Gents,
I have a question about a fillet weld burn through (melt through).
We have welded a strip (5 mm thick 16Mo3) to a pipe (60,3 x 4 mm SA-210 grade A1)
During the visual inspection by our client, they discovered a burn through (only a few tenths)
The pipe is a part of a membrane panel (evaporator).
Technically there isn't a issue but our client want us to repair the tube.
I searched in the ASME BPVC section I but it doesn't say anything about a burn through.
Can the customer technically reject our work?
Thanks in advance,
Bas
I have a question about a fillet weld burn through (melt through).
We have welded a strip (5 mm thick 16Mo3) to a pipe (60,3 x 4 mm SA-210 grade A1)
During the visual inspection by our client, they discovered a burn through (only a few tenths)
The pipe is a part of a membrane panel (evaporator).
Technically there isn't a issue but our client want us to repair the tube.
I searched in the ASME BPVC section I but it doesn't say anything about a burn through.
Can the customer technically reject our work?
Thanks in advance,
Bas
RE: Fillet Burn Through ASME BPVC Section I
IMHO the issue (if any) would be the chemical composition of the melt through material.
You have P3 material welded to a P1 pipe - what is the as welded chemical composition and is there a possibility it may react differently with whatever product is flowing through the pipe ?
RE: Fillet Burn Through ASME BPVC Section I
The as welded composition is like 16Mo3 (P3) which is quite common for power plants. The medium is demineralized water / steam.
Furthermore the fillet weld has been qualified by a but weld (SA106 grade B to 16Mo3).
So the burn / melt through is covered by a valid PQR.
I don't see why the tube should be repaired.
RE: Fillet Burn Through ASME BPVC Section I
After I made my original post I had a couple of thoughts - why did you burn through ?
1 The variables (amps/volts/travel speed) listed on the WPS (I presume you had a fillet weld WPS ?) were incorrect for the thickness being welded.
or
2 The welder did not follow the variables listed on the WPS.
Either of these are legitimate reasons for the client to reject the weld/s,
Regards,
Shane
RE: Fillet Burn Through ASME BPVC Section I
RE: Fillet Burn Through ASME BPVC Section I
RE: Fillet Burn Through ASME BPVC Section I
The burn through is probably induced by spacing between the plate and the pipe. Due to this the welding speed has been reduced and resulted in the burn through.
Regarding the heat input isn't a essential but a supplementary essential.
@ mk3223, what about the circumferential (butt) welds in the tube, they can also be a potential failure.
I talked to my authorized inspector and also he sees no reason to disapprove.
RE: Fillet Burn Through ASME BPVC Section I
RE: Fillet Burn Through ASME BPVC Section I
RE: Fillet Burn Through ASME BPVC Section I
RE: Fillet Burn Through ASME BPVC Section I
Generally, the customer can't unilaterially make up new rules as the project progresses.
Best regards - Al