Temporary Stream Crossing
Temporary Stream Crossing
(OP)
I work for a firm that primarily does sanitary sewer rehab studies. In our most recent project, the contractor put in a temporary stream crossing that consisted of a CR-6 (crusher run) culvert and corrugated metal pipe, as per the Maryland Sediment and Erosion Control Design Manual. To make a long story short, we had an unusually large rainfall and the culvert was washed out. So now we're evaluating alternative stream crossings and we had a couple of ideas.
A little background about the stream: approximately 30 to 40 feet wide, slow flowing, about 12-18" deep under dry weather conditions, rocky or sandy bottom.
Several ideas have been floated for a new crossing:
1. Bailey bridge (expensive, lack of contractor experience)
2. Concrete box culverts overlaid with wood construction mats (access issues with the crane required to set the boxes, expense)
3. Stone culvert constructed with gabion mats and corrugated or concrete pipe
The culvert has to stay in place for 2 months so that work can continue during an instream construction prohibition due to the trout spawning season. Basically we're looking for a solution that's cheap, low maintenance, and requires minimal structural engineering (none of us are). Just thought I'd see if anyone else had success with a stream crossing. Thanks.
A little background about the stream: approximately 30 to 40 feet wide, slow flowing, about 12-18" deep under dry weather conditions, rocky or sandy bottom.
Several ideas have been floated for a new crossing:
1. Bailey bridge (expensive, lack of contractor experience)
2. Concrete box culverts overlaid with wood construction mats (access issues with the crane required to set the boxes, expense)
3. Stone culvert constructed with gabion mats and corrugated or concrete pipe
The culvert has to stay in place for 2 months so that work can continue during an instream construction prohibition due to the trout spawning season. Basically we're looking for a solution that's cheap, low maintenance, and requires minimal structural engineering (none of us are). Just thought I'd see if anyone else had success with a stream crossing. Thanks.
RE: Temporary Stream Crossing
RE: Temporary Stream Crossing
RE: Temporary Stream Crossing
In my experience, I have usually elected (or been forced) to work outside of spawning seasons or habitat restrictions (in reference to seasonal restrictions).
Are you laying pipe and crossing the stream? If so, it would cheaper and less headaches (maybe less headaches only) if the pipe was augered, directionally drilled or tunneled under the stream. That's the plan "B" I have incorporated too.
KRS Services
www.krs-services.com
RE: Temporary Stream Crossing
RE: Temporary Stream Crossing
Up here, due to regulatory requirements regarding working within a habitable (fish bearing) stream the contractor does not specifiy any mehodology whatsoever. The engineer must provide a specified temporary crossing and remedial measures once completed. This design and methodology is then reviewed and approved by the governing authority and then put into the contract for tender.
Failing to do this could result in, and I'm not kidding, arrests and steep fines for the Owner (which could be a Provincial government) the engineer and the contractor.
If a blowout has already occurred, I suggest to "etd" that the contractor provide a "shop drawing" as to how they intend to deal with the stream flows, review it as the project engineer and submit for regulatory approval. Given the concern of trout spawning, I suspect the regulatory authority has already raised the flags about working in the stream. Getting their approval will go a long way to a hassle free project, both from a project perspective and public viewpoint (environmental weenies). As I mentioned earlier, if it is possible to not disturb the stream bed any further, I would explore that first as an option.
KRS Services
www.krs-services.com
RE: Temporary Stream Crossing