holdpt
Structural
- Oct 10, 2011
- 82
I found through a search where #31 was addressed and the summary was that any CJP groove qualifies for any other groove with details meeting 3.12 and 3.13. But then there was no addressing of #32 which seems contradictory to #31. My question is then if a prepared CJP groove is qualified per section 4, does that PQR apply to all as stated in #31 or all except square grooves which seems to be what #32 states?
THanks!
THanks!