INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

solver time

solver time

solver time

(OP)
I am running a simulation in Solidworks. I have 11 grounded bolt fixtures and 14 bolt connectors. The other components have a mixture of 'bonded' and 'no penetration' contact sets. There are 13 contact sets and another 13 component contact sets. There are four parts in the assembly and additional 13 gussets.

My computer has 8 GB memory and the resources seem to be enough (checked performance in task manager)
My solver has been running for the past hour and 40 min. and for at least the past 20 minutes (mayb longer as this is when I checked before) the solver is at 9.1% The details of the solver show it at 100% of 'Automatic global contact search'. There has no change in the memory usage for a looong time. Though task manager shows fluctuating CPU usage.


Now, my question, Should I cancel this analysis or leave it running? Is it stuck for worse?
Replies continue below

Recommended for you

RE: solver time

Sounds pretty typical for lots of contacts and based on your description I would say it would take a long time to run. RAM is important if you have heaps of nodes but with contacts it is just a waiting game with standard processors.

You can probably rationalise your analysis quite a bit. Some of the contacts could be changed to bonded for simplicity or removed by sub-modelling. Or if you are using surface to surface contacts you could change this to edge to surface. You can add a series of split lines for edge contacts to simulate a full surface.

There may also be options to simplify your geometry and maybe use symmetry if possible.. To check if you can remove some contacts run the simulation really rough with a draft mesh and see which components behave as essentially bonded then change your inputs. Check your reactions and make sure all is good.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close