INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Prying loads on bolts.

Prying loads on bolts.

Prying loads on bolts.

(OP)

We have a piece of equipment with steel side frames of a given distance from each other; 1.25 thk plates parallel to each other with cross bars. We need to mount this on top of a similar piece of equipment with a side frame to side frame distance a few inches wider or narrower than ours. A solution we have tried is to bolt an adaptor plate to the top of each side frame that steps inboard or outboard a few inches to provide a platform for the next piece of equipment. The best description I can give it to imagine cantilever that is very short and very wide and bolted along the wide edge. We have approached this assuming that if the moment due to the eccentric load (load at the end of the cantilever X cantilever length) is less than what is required to open the joint we are ok. Spanning the side frames with a beam is not always possible due to machine function.

jaggmi

RE: Prying loads on bolts.

jaggmi want is the question

RE: Prying loads on bolts.

(OP)
My question above relates to 1) the practice of using bolts in a configuration where a prying load is the main load being resisted. 2) If this practice is ok is our assumption about using a pre-stress value on the bolt that keeps the joint closed is a good guide for designing such a joint?

RE: Prying loads on bolts.

1) This practice is discouraged because the eccentric loading decreases joint force resistance and increases the chance of damaging the bolt.

2) If you must use this configuration, then yes you design with the pre-stress that prevents joint opening.  This topic is covered in VDI 2230, Systematic Calculation of Bolted Joints available at:

http://www.beuth.de

RE: Prying loads on bolts.

Is VDI 2230 available in English?  Our librarian claimed it's available only in German, but I wonder if I should ask them to check again.  Thanks.

RE: Prying loads on bolts.

VDI 2230 is available in English - I have the 1986 translation, although a new one is supposed to be published very soon.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close