Actual start and actual finish dates are changing start & finish
Actual start and actual finish dates are changing start & finish
(OP)
I added an actual start and actual finish columns to my project plan in the gant chart view. When I try to update the actual start and actual finish dates, it changes the start and finish dates. I must be doing something wrong. Any help would be appreciated. Thanks
RE: Actual start and actual finish dates are changing start & finish
Ellen Lehnert, PMP, MCT
Certified MS Project/MS Project Trainer
www.lehnertcs.com
RE: Actual start and actual finish dates are changing start & finish
RE: Actual start and actual finish dates are changing start & finish
RE: Actual start and actual finish dates are changing start & finish
RE: Actual start and actual finish dates are changing start & finish