MS Project 2007 question
MS Project 2007 question
(OP)
hello,
i'm creating a schedule in project.....and i have the following question: (ps. i'm very new at this)
how do i indicate the predecessor if i have a "task" C that can be started when 'either' task A or task B is completed?
thank you
i'm creating a schedule in project.....and i have the following question: (ps. i'm very new at this)
how do i indicate the predecessor if i have a "task" C that can be started when 'either' task A or task B is completed?
thank you
RE: MS Project 2007 question
Which every task out of A and B is later will determin the starting date of Task C.
Good luck!