Jun 24, 2009 #1 j33pguy Aerospace Joined Jun 24, 2009 Messages 1 Location US hello, i'm creating a schedule in project.....and i have the following question: (ps. i'm very new at this) how do i indicate the predecessor if i have a "task" C that can be started when 'either' task A or task B is completed? thank you
hello, i'm creating a schedule in project.....and i have the following question: (ps. i'm very new at this) how do i indicate the predecessor if i have a "task" C that can be started when 'either' task A or task B is completed? thank you
Jul 1, 2009 #2 WhiteyWhitey Electrical Joined Feb 3, 2009 Messages 61 Location AU Create Linkages between Both task A and B and Task C. Which every task out of A and B is later will determin the starting date of Task C. Good luck! Upvote 0 Downvote
Create Linkages between Both task A and B and Task C. Which every task out of A and B is later will determin the starting date of Task C. Good luck!