Offshore pipeline installation start-up
Offshore pipeline installation start-up
(OP)
Dear all,
What is the pros and cons of using single cable mooring attached to one of the platform jacket leg for start-up of offshore pipeline laying?
What is the pros and cons of using single cable mooring attached to one of the platform jacket leg for start-up of offshore pipeline laying?
RE: Offshore pipeline installation start-up
1] Easy to install
2] Flexible to manoveure the barge
3] Easy to connect the fuse soft rope
Cons:
1] Too much load at one point on the jacket leg
2] Larger tolerance on the target point
3] Target point would much away from the jacket base requiring longer riser tie-in spool
4] Most operators would not allow
Narendranath R
Pipeline engineering is made easy with state of the art computer software, visit www.narendranath.itgo.com.
RE: Offshore pipeline installation start-up
is there any bad effect to the linepipe itself, i.e. stress, span length, fatigue, etc. ?
RE: Offshore pipeline installation start-up
The installation analysis will take care of the stresses.
Narendranath R
Pipeline engineering is made easy with state of the art computer software, visit www.narendranath.itgo.com.
RE: Offshore pipeline installation start-up