INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

NPD Process Toll gate approvals

NPD Process Toll gate approvals

NPD Process Toll gate approvals

(OP)
I am looking for some tips on handling phase type approvals in a NPD environment.

Any suggestions?

RE: NPD Process Toll gate approvals

Assuming you have a list of requirements that need to be addressed at each gate, I would recommend putting them into some sort of speadsheet with a "status indicator" as to whether the requirement has been met, is in process, or has not been met/addressed.  You can then put this into presentation software for the review meeting(s).  You could have additional slide(s) if needed providing further details.

The indicator sheet may work well for you for both the product team and for reporting purposes to management.

Regards,

RE: NPD Process Toll gate approvals

We have two documents at every gate - a project file audit and a gate approval form.  The first is a checklist that shows if the required docs to pass that gate (e.g. previous gate approval, signed-off design requirements, patent review form, etc...) are present, not present, or not applicable.  The project manager initials these.

The second lists the requirements (e.g. concept agreed, patent review complete, mfr site decided, etc...) for advancing the project to the next phase with spaces for the decision makers (business unit, engineering, maybe operations) to sign.

These are standard lists depending on project level and gate number.  We also have standard presentation formats for each gate that allows the project manager to present the required info to the team/ stakeholders.  

RE: NPD Process Toll gate approvals

(OP)
So the basic thing is the phase approval is handled with a meeting.

We were trying to do it with e-mail and it does not work.

RE: NPD Process Toll gate approvals

I could see final approval being electronic but I'd have thought you'd want a get together for the PM to give a presentation on status etc and explain any 'orange' or 'red' areas & put forward justification/mitigation for why you should still go to next phase.

Out of our meetings a few actions will often come up, these will be addressed and then approval will be given.

KENAT,

Have you reminded yourself of FAQ731-376: Eng-Tips.com Forum Policies recently, or taken a look at posting policies: http://eng-tips.com/market.cfm?

RE: NPD Process Toll gate approvals

Sometimes meetings actually are a good thing.  For phase gate reviews, I believe them to be necessary.  A lot of things can get captured in a meeting that would not necessarily come up in e-mail threads.

Regards,

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close