How can I create a baseline percent vs normal work percent
How can I create a baseline percent vs normal work percent
(OP)
I need to compare a real work percent with a baseline work percent. Example
Start End baseline start baseline finish %Real %planned
Oct03 Oct31 Oct01 Oct28 80% ?
If someone can help me
thanks a lot
Start End baseline start baseline finish %Real %planned
Oct03 Oct31 Oct01 Oct28 80% ?
If someone can help me
thanks a lot
RE: How can I create a baseline percent vs normal work percent
Baseline Start and Baseline Finish get populated from Start and Finish at the time we save the Baseline. Microsoft Project does NOT copy % Complete into a Baseline % Complete column. Even if it did...wouldn't most of the % Commpletes be 0 at the time of baselining?
You might try this: Instead of %planned, I might call it Expected % Planned. Then use this formula:
ProjDateDiff([Start date];Date();[Project Calendar]))*100)/([Duration]
Hope this helps!!
J Black
www.pmconnection.com