Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

How can I create a baseline percent vs normal work percent

Status
Not open for further replies.

niyiredmg

Computer
Oct 29, 2008
1
I need to compare a real work percent with a baseline work percent. Example
Start End baseline start baseline finish %Real %planned
Oct03 Oct31 Oct01 Oct28 80% ?

If someone can help me
thanks a lot
 
Replies continue below

Recommended for you

hhhmmmmm
Baseline Start and Baseline Finish get populated from Start and Finish at the time we save the Baseline. Microsoft Project does NOT copy % Complete into a Baseline % Complete column. Even if it did...wouldn't most of the % Commpletes be 0 at the time of baselining?

You might try this: Instead of %planned, I might call it Expected % Planned. Then use this formula:
ProjDateDiff([Start date];Date();[Project Calendar]))*100)/([Duration]

Hope this helps!!

J Black
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Top