INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Fixed Duration Tasks Slifing Towards Completion Date

Fixed Duration Tasks Slifing Towards Completion Date

Fixed Duration Tasks Slifing Towards Completion Date

(OP)
Is there a way to create fixed duration tasks, or view tasks in a manner that shows me the situation as it would look if the task started today (or on a status date set for today)?

Background:

I have 5 Engineering Orders to release for every aircraft.

They are standardization EOs.

Each aircraft is setup as an individual project with a definite finish date, 90 days before it comes into the hangar for work.

I schedule each aircraft a small 5 task project, from the finish (completion) date.

It doesn’t make sense to lay in fixed start and stop dates for any EO (tasks).

The situation is too fluid.

Each of the 5 EOs have different fixed durations.

One engineering order defines the work on multiple aircraft (based on configuration similarities in that system).


I don't track progress on any EO, It's either released (completed) or it's not.

The EOs don’t need to be released in any particular order.


All of the aircraft projects are imported into a master project for the fleet.

I use the master project to mark completions as each EO is released.

I also use it to see what EO durations are too close to what deadline on which aircraft to determine what needs to be worked next.

I'm managing as many as 20 aircraft projects in a fleet.

At any time, I may have to go in individual aircraft projects and change the completion date (or hangar date) as capacity changes around the system.


Any help is appreciated.

Thanks,
Replies continue below

Recommended for you

RE: Fixed Duration Tasks Slifing Towards Completion Date

Use the Tracking Gantt view, save a baseline, then modify

TTFN



Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close