Project 'Working Hours'
Project 'Working Hours'
(OP)
Is there any way of specifying working hours by sub-project within a single plan ? I'm trying to tie sub-projects together in the same plan. The sub-projects are fixed durations but have different default working hours, e.g. one works weekends, the other doesn't. At the moment I am having to work off estimated start and end rather than duration. If the dates slip, then the durations will be wrong if they fall over an extra weekend.
RE: Project 'Working Hours'
I hope the following solution will work for you
- define seperate calenders for various sub projects
tools->change working time ->new calender
- Say you have defined calender1 for sub project1
now select this calender (tools->change working time-calender1) and now select non default working time for this calender, for this you will select a column (say monday column) on the calender and on the right side of this display you have the columns to specify the working hours.
-Now for sub project 1 , the task you have defined , modify them for calender=calender1 (go to advance tab on task information popup)