Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Project 'Working Hours'

Status
Not open for further replies.

SBuddS

Aerospace
Jan 29, 2002
5
Is there any way of specifying working hours by sub-project within a single plan ? I'm trying to tie sub-projects together in the same plan. The sub-projects are fixed durations but have different default working hours, e.g. one works weekends, the other doesn't. At the moment I am having to work off estimated start and end rather than duration. If the dates slip, then the durations will be wrong if they fall over an extra weekend.
 
Replies continue below

Recommended for you

Hi
I hope the following solution will work for you
- define seperate calenders for various sub projects
tools->change working time ->new calender
- Say you have defined calender1 for sub project1
now select this calender (tools->change working time-calender1) and now select non default working time for this calender, for this you will select a column (say monday column) on the calender and on the right side of this display you have the columns to specify the working hours.
-Now for sub project 1 , the task you have defined , modify them for calender=calender1 (go to advance tab on task information popup)

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor