How do you manage work effort as compared to duration
How do you manage work effort as compared to duration
(OP)
I like to put start and end dates on each task, thinking about how many days I am giving a resource to complete a task. I although do not know how to input the work effort it will take to complete the task during the duration. Please help as I need to do a resource risk analysis and dont know how to get started.
RE: How do you manage work effort as compared to duration
However, if you have more than one person working a job, then the hours are doubled, or, if you only have a 1/2 head on the job, then the hours are only 1/2.
Also, if that 1/2 person is working 1/2 time on a different task, then your resource page will show his correct loading.
TTFN
RE: How do you manage work effort as compared to duration
RE: How do you manage work effort as compared to duration
TTFN