A friend of mine asked me to complete the pre and post construction runoff calculations for this proposed 0.53 acre site. They are constructing a 45x70 metal building. The parking lot is existing, and other than that the existing pre-construction conditions are empty grass lot.

The county in question wants to see net zero increase to runoff, post construction. Any ideas? A detention pond for a development this size seems to be overkill.

There is a drainage swale on the north end of the property that runs the entire length to the main ditch by the road.
 
 https://files.engineering.com/getfile.aspx?folder=15841ce1-df88-4a1b-87dc-4e0e2f35cfe6&file=Project.png
Agree with bimr, always chat with approving agency for adherence to code/criteria.
 