msesi
Materials
- May 15, 2010
- 21
I'm currently constructing an asphalt concrete road of 5cm thick.During the design the Contractor has added 2%cement as an active filler in the mix proprortions(different types of aggregate+5%bitumen and2%active filler(cement).However the supervidsion team carriedout some mix design and found that the asphalt fullfilled all requirements without additional of active filler.In the Bill of Quantities an item of active filler is there,but to be used an authoprity must first required from the Engineer.It has been given as a Provisional sum.If this item of active filler is not incorporated in the work,will it have a decrimental effect to the asphalt concrete in the future??The road is constructed in hot areas.Please assist as the Contractor is currently pushing the Engineer to use the active filler in the production of the asphalt concrete.