Ron247 - Bridge deck thickness varies with span length and design. We built bridges with decks from 8" to 24" thick. Overhangs are typically 8 or 9 inches thick. However, overhang brackets are not needed or used for construction of all bridge designs.
The 75 plf is really for the manufacturer's design of the brackets, Contractor does not need that info.
All forming for the bridge deck and the overhang brackets are removed before the parapet is placed. Pouring parapet is allowed to lag well behind slab placement. This is for several reasons:
1) The weight of the parapet is designed to be supported by the slab; brackets are not needed.
2) The brackets may be overloaded if they remained in place and the additional load / deflection could make removing them dicey.
3) Allowing the slab to fully cure means the concrete truck can drive right up to the parapet placement and pour concrete directly out of the truck (instead of using a crane / concrete bucket).
4) A bridge contractor probably has a limited number of brackets, he has to keep leap-frogging all the forming, including the brackets, to keep superstructure construction moving along.
5) A bridge contractor probably has a limited length of (steel) form for the face of New Jersey barrier. He keeps this set up, ready to go, and waits for an opportunity to make a parapet placement... say, with concrete "left over" after placing a slab. Divert that concrete to pour a limited length of parapet. Only takes 2 1/2 yd
3 for a 15' length of parapet. Parapet is designed to be placed in segment with gaps at slab joints and perhaps in between. A 15' placement is just right for half of a 30' span... a popular length in our area.
![[idea] [idea] [idea]](/data/assets/smilies/idea.gif)