A fabricator was told to weld a 6" lateral pipe to a 10" main pipe with a fillet weld. The line is chilled water at 20 psi. It was tested to 150 psi, and held.
ASME B31.1, pg 75, fig 127.4.8, dwg A (I don't have this if someone could provide it) apparently discusses a CJP weld, not a fillet?
Is it acceptable to leave the fillet weld with subsequent testing? If not, is there a fix such that a reinforcing ring or something could be added in a CJP manner to accomplish this?
Any help is much appreciated.
ASME B31.1, pg 75, fig 127.4.8, dwg A (I don't have this if someone could provide it) apparently discusses a CJP weld, not a fillet?
Is it acceptable to leave the fillet weld with subsequent testing? If not, is there a fix such that a reinforcing ring or something could be added in a CJP manner to accomplish this?
Any help is much appreciated.