javan210
Mechanical
- Mar 26, 2010
- 13
Dear Friends,
We are going to test a piping system which includes some underground and aboveground piping sections.
The system shall be tested as one package.
Can we eliminate the weld joints visual inspection for underground portion? (because we have to perform the wrapping before hydrotest).
Thank you
We are going to test a piping system which includes some underground and aboveground piping sections.
The system shall be tested as one package.
Can we eliminate the weld joints visual inspection for underground portion? (because we have to perform the wrapping before hydrotest).
Thank you