hrdrok
Mining
- Jan 11, 2010
- 4
Got pointed here from civil guys
Simple (or not),
I need to move ~10,000 usgpm of water over 3000 feet, in subartic conditions, 24/7 run conditions.
Pipe is fully exposed, free draining both ends.
Negligible head (10m +/-) plus line loss.
Heat trace and insulated pipe not an option due to cost.
Mining application
Anybody have a minimum flow velocity to prevent line freezing,Probably sclair DR17, water at low single digits (2-3 degC).
Ambient air temp -20C and warmer.
ANy ideas?
h_r