gsail
Mechanical
- May 24, 2004
- 3
I just started the design work for a replacement tray tower for a local refinery. They want it built pretty much as is but to meet their current specs and reuse existing ladders & platforms. This vessel has 7 vacuum stiffening rings for external pressure. Two of the rings pass through nozzles and one of the two actually passed through 3 nozzles. I have never designed a vessel that this was done and always considered it bad practice. Compress shows it as a deficiency in the report, but not as a failure. The customer specs say nothing about the practice, the vessel was built prior to the current company's ownership of the plant. Is this a viable method of placement of the rings? I am looking a moving the rings as an alternative but there are plenty of other interferences that will make that difficult. I have put a call out for our AI to get his views. Any of you out there dealt with something similar?