Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Underpinning a spread footing

Status
Not open for further replies.

PBEIT

Structural
Sep 9, 2013
13
I have an 8ft square spread footing supporting approx. 20K. I need to get a wall along side it that will only be two feet away from the spread footings edge and the depth from the bottom edge of the spread footing to the bottom edge of the walls strip footing is four feet. I don't have any information on the existing soil conditions. Can I excavate up at an angle from the required depth of the strip footing to half way under the spread footing at(approx. 45 deg.) and do 3 pours, something like: 1. excavate in 1-1.5ft from the footing edge on one side 2. do the other side the same way and then 3. do the remaining 5-6ft in the middle? Any advise would be greatly appreciated.

Thanks, pbeit
 
Replies continue below

Recommended for you

Without soil data, it is difficult to advise. However, with that light bearing pressure, it is likely that any thoughtful approach would work. consider a lip on the new wall to support one edge of the old footing. That minimized chances of pushing the new wall away from the old footing.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor