dcjones
Structural
- Sep 5, 2017
- 3
I am designing traditional pit underpinning for a new addition with basement in an existing building. The building is a lightly loaded one story structure with a 2 ft wide concrete wall footing about 3 ft below existing grade. The new basement's bottom of footing will be 10 ft below the building's slab (7 ft below bottom of existing footing). The new basement wall's proximity to the existing building is along a slope and varies from 0' to 7' away.
The soils are an elastic silt with an internal friction angle of 25 degrees. The geotech. engineer has provided an EFP of 50 psf and 3,000 psf allowable bearing for the pins with this soil.
Unfortunately, after doing the calculations for the pins the soil is not able to stabilize the pins without a tie anchor or rakers. Due to the lightly loaded structure there is not enough weight on the pins to control the sliding / overturning with the relatively large lateral loading.
I would like to use rakers instead of tiebacks to limit mobilization of equip for soil anchors and avoid drilling below the building. Although the concern with rakers is the interference with the new wall and footing due to them being required to go through the new foundation wall.
Does anybody have experience using rakers instead of tie backs? Lateral force would be roughly 20 kips for rakers at 8' o.c. Would they be cheaper then soil anchors?Estimate 15 (rakers/tiebacks req'd)
I am also looking for details for the raker to underpin / deadman connections if anybody has some input would be helpful.
Thanks.
The soils are an elastic silt with an internal friction angle of 25 degrees. The geotech. engineer has provided an EFP of 50 psf and 3,000 psf allowable bearing for the pins with this soil.
Unfortunately, after doing the calculations for the pins the soil is not able to stabilize the pins without a tie anchor or rakers. Due to the lightly loaded structure there is not enough weight on the pins to control the sliding / overturning with the relatively large lateral loading.
I would like to use rakers instead of tiebacks to limit mobilization of equip for soil anchors and avoid drilling below the building. Although the concern with rakers is the interference with the new wall and footing due to them being required to go through the new foundation wall.
Does anybody have experience using rakers instead of tie backs? Lateral force would be roughly 20 kips for rakers at 8' o.c. Would they be cheaper then soil anchors?Estimate 15 (rakers/tiebacks req'd)
I am also looking for details for the raker to underpin / deadman connections if anybody has some input would be helpful.
Thanks.