I am looking at repairing some underground 3" (200F 50 psig design/ 125F 25 psig operating). The pipes don't see a ton of flow (I am not able to give an exact number), and one goes under the slab and straight across, the other has 2 elbows before coming up through the slab. We are trying to repair the pipes without digging up the slab. The reason for the replacement is FAC, localized corrosion in places and it has been determined something needs to be down during the next shutdown. One of my fellow employees who I'm working with is going to BPIG next week and will inquire about what some other engineers have been successful doing. I figured I would ask on here if anyone has any experience on here that would help.