Arba
Electrical
- Jan 21, 2010
- 5
Anybody can tell me if I set to block the under voltage protection on a main 5 KV BUS, when one of the relay PT fuses would blows (The 27 Relay has the feature to supervise the PT voltage), with the excuse that probability of two events: under voltage phenomena and PT Relay Disruption happening in the same time would be very slim. At the end I can eliminate the main breaker trip when a PT fuse is blown, by just alerting the personnel to replace the fuse in a better time.