sramesh
Mechanical
- May 12, 2003
- 42
Good day to you
Our consultant recommends U/f & df/dt relays setting with 100msec time delay for load shedding scheme (4 stages of load shed from 48.5 to 47.8 @ 1 Hz/sec)to avoid black out in case one/few generators sudden trip.( our electrical system is with own generation and no link with Grid)
My query is, Delay of 100 msec, will it be sufficient? will it cause spurious trip during a system equipment fault ( short circuit or groud fault), which may take more than 100 mSec to clear the faulty cicuit.
Thanks in advance for your clarification
Our consultant recommends U/f & df/dt relays setting with 100msec time delay for load shedding scheme (4 stages of load shed from 48.5 to 47.8 @ 1 Hz/sec)to avoid black out in case one/few generators sudden trip.( our electrical system is with own generation and no link with Grid)
My query is, Delay of 100 msec, will it be sufficient? will it cause spurious trip during a system equipment fault ( short circuit or groud fault), which may take more than 100 mSec to clear the faulty cicuit.
Thanks in advance for your clarification