Fizza453
Mechanical
- Jun 22, 2011
- 262
I get quotation from dish head supplier, material is P.No.1 Group No. 2 (SA-516-70).
Plate is normalized. Dish head shall be formed by hot forming in normalization range at approx. 900 degree C. Dish head is seamless.
Now, per UCS-85 simulated heat treatment is required.
Vessel is required to be post weld heat treated at 600C for 130 minutes.
Which of the following heat treatment shall be performed on the test plate to meet UCS-85?
1- Normalization at 900C@time plus 600C@time.
2- Only normalization at 900C@time
Nasir
Welding Engineer
DESCON ENGINEERING LIMITED
PAKISTAN
Plate is normalized. Dish head shall be formed by hot forming in normalization range at approx. 900 degree C. Dish head is seamless.
Now, per UCS-85 simulated heat treatment is required.
Vessel is required to be post weld heat treated at 600C for 130 minutes.
Which of the following heat treatment shall be performed on the test plate to meet UCS-85?
1- Normalization at 900C@time plus 600C@time.
2- Only normalization at 900C@time
Nasir
Welding Engineer
DESCON ENGINEERING LIMITED
PAKISTAN